35 Workers Are Employed To Complete. A Construction Project In 16 Days. Before The Project Starts, The Boss Of The Company Is Told That He Needs To Complete The Project In 14 Days. Assuming That All The Workers Work At The Same Rate, How Many More Workers Does He Need To Employ In Order To Complete The Project On Time?

A. 3
B. 4
C. 5
D. 9
Submitting...

🚀 Found an error or have a suggestion?

Your feedback helps us keep our MCQs accurate and up-to-date.

We appreciate your contribution to improving the quality of our MCQs.

Related MCQs

Related MCQs where subject and topic are same as this mcq

Question 1: Who among the following is the current Secretary General of SAARC?

Medical Jobs Mock Test Solved Papers

Question 2: Who was the first governor general of the State Bank of Pakistan?

Technical Jobs Entrance Exams Business Studies
AI medium

Question 3: The capital of Chechnya is:

Teaching Jobs Practice Tests Quizzes

Question 4: World polio Day is celebrated on :

Competitive Exams English Premium MCQs